GE Renewable Energy announced on May 18 that it has finalized the Turbine Supply and Service and Warranty contracts for the third and final phase of the Dogger Bank offshore wind farm, Dogger Bank C. (Photo quoted from GE’s website)

 

The Turbine Supply Contract confirms that GE Renewable Energy will provide 87 units of the Haliade-X 14 MW offshore wind turbine, marking the first commercial commitment for this nameplate. The Haliade-X 14 MW is an upscaled version of the Haliade-X 13 MW, the most powerful offshore wind turbine in operation today. The contract is subject to financial close for Dogger Bank C which is expected in late 2021.

 

GE Renewable Energy and Dogger Bank have also finalized the Service and Warranty Contract for a five-year full-service agreement that will begin once the Dogger Bank C phase is commissioned in 2026.

 

GE Renewable Energy has now finalized all contracts for the 3.6 GW Dogger Bank Offshore Wind Farm, due to become the largest offshore wind farm in the world upon completion.

 

GE Renewable Energy expects to create up to 300 direct jobs during the installation of the three consecutive phases of Dogger Bank project, this number includes the 120 positions already announced that will be based in Teesside from Able Seaton Port.

 

Also, in addition to the 120 jobs announced following the Service and Warranty contracts for Dogger Bank A and B, the company would add up to roughly 50 new operations and maintenance jobs to be based from the Port of Tyne for Dogger Bank C. 

 

This would represent a total of estimated 470 new skilled jobs created to support the Dogger Bank project.

 

Dogger Bank C is owned by SSE Renewables (50%) and Equinor (50%), while Dogger Bank A and B are owned by SSE Renewables (40%), Equinor (40%) and Eni (20%). As previously announced, Dogger Bank A and B phases will be the first to feature GE’s Haliade-X 13 MW, with a total of 190 to be installed. Today’s confirmation of an additional order of 87 upscaled Haliade-X 14 MW turbines for Dogger Bank C brings the total number of Haliade-X units to be installed at Dogger Bank to a total of 277.

 

Dogger Bank Wind Farm is located over 130 km off the north-east coast of England and each phase will be able to produce 6TWh of renewable electricity, totaling 18TWh annually, when complete in 2026, equivalent to powering approximately the equivalent of six million UK homes each year or around 5% of the UK’s electricity demand. Due to its size and scale, the site is being built in three consecutive phases: Dogger Bank A, Dogger Bank B and Dogger Bank C. Each phase is expected to generate around 6 TWh of electricity annually.

 